480                           GST LAW TIMES                      [ Vol. 36
                                                      3.2  Notwithstanding  the  break-up of the  Contract Price, the  Con-
                                                      tract shall, at all times, be construed as a single source responsibility
                                                      Contract and any breach in any part of the Contract shall be treated as
                                                      a breach of the entire Contract.
                                                      5.  For release of advance payment (admissible as per the Bid-
                                                      ding  Documents) equal  to 10% of the Ex-works Price compo-
                                                      nent of the Contract Price for Main Equipment (excluding
                                                      spares), you are, inter alia, required to furnish Bank Guarantee
                                                      for the equivalent advance amount, as detailed at APPENDIX
                                                      (N0A)-3. Further, please note that furnishing of all the Contract
                                                      Performance Securities under the ‘First Contract’, ‘Second Con-
                                                      tract, ‘Third Contract’, ‘Fourth Contract’, ‘Fifth  Contract’  and
                                                      ‘Sixth Contract by the JV and Contract Performance Securities
                                                      under “Third Contract’ and ‘Fifth Contract’ by you (Associate of
                                                      the JV i.e. SIEMENS-1) shall be one of the conditions precedent
                                                      for release of advance under this Contract.
                                                      7.  The schedule for Taking Over/Time for Completion of the
                                                      Facilities  by the Employer upon successful completion of the
                                                      +320KV,  2X1000MW VSC  based  HVDC Terminals and DC
                                                      XLPE Cable system between Pugalur and North Trichur associ-
                                                      ated with HVDC Bipole link between Western region (Raigarh,
                                                      Chhattisgarh)  and Southern region (Pugalur, Tamil Nadu-
                                                      North Trichur, Kerala) and the Additional Time for Completion
                                                      for all contractual purposes in  line with the provisions of the
                                                      Bidding Documents shall be as follows :

                                                      Sr.      Completion (Taking Over) of :    Duration
                                                      No.                                       from the
                                                                                                effective
                                                                                                 date of
                                                                                                contract
                                                      Time for Completion
                                                      1.   +320KV, two 1000MW Voltage Source Con-
                                                          verter (VSC)  based HVDC transmission
                                                          system between Pugalur (Tamil Nadu) and
                                                          North Trichur (Kerala)
                                                          a.  Monopole 1 and associated  Cable sys-  38 months
                                                             tem
                                                          b.  Monopole 2 and associated  Cable sys-  38 months
                                                             tem
                                                          Additional Time for Completion# : 30 weeks

                                                      # Additional Time for Completion shall be subject to levy of
                                                      Liquidated Damages (LD) as per provisions of Bidding Docu-
                                                      ments’
                                                      * The Time for Completion (Taking Over) for the Replica along
                                                      with Real Time Simulator and IPSRTS for real time studies in-
                                                      cluded in the above Facilities will be 45 months.
                                                      8.  This Notification of Award constitutes  formation of the
                                                      Contract and comes into force with effect from the date of issu-
                                                      ance of this Notification of Award.