Page 169 - GSTL_23rd April 2020_Vol 35_Part 4
P. 169

2020 ]                      IN RE : ABB INDIA LTD.                   495
                       (2)  Supply, laying  and connecting of the  control cables  from  RTU  to
                           equipment,
                       (3)  Supply, erection and commissioning of UPS and batteries for RTU,
                       (4)  Supply and installation of slave clocks and antenna,
                       (5)  Modification of software  at  OCC  to accommodate  new RTUs and
                           installation of software in RTUs at Baranagar and Dakshineswar,
                       (6)  System check, testing and commissioning of SCADA for full control,
                           protection, telemetering including data logging,
                       (7)  Supply and commissioning of LCD  screen with  accessories  at Re-
                           mote Control Centre,
                       (8)  Freight and insurance.
                       2.3  The  Applicant submits that  it is  evident from the Technical Offer
               (refer to Annexure D to the Application) that the supply involves designing, en-
               gineering, manufacturing, site  installation, cable  laying, erection, testing, com-
               missioning etc. The contract, therefore, involves supply of both goods and ser-
               vices. RVNL will release 30% of the payment only after the erection and commis-
               sioning are completed. Even the payment for freight and insurance will be made
               after the erection work is completed. It is clear, therefore, that the contracts for
               supply of goods and that of services are not divisible and the entire contract for
               the supply of SCADA is a composite supply of goods and services.
                       2.4  The Applicant further submits that erection and commissioning of
               RTUs at a specified location for a metro project is a work of permanent nature.
               The cables laid cannot be shifted without causing substantial damage. Such shift-
               ing will render such cables  incapable of further use.  In short, SCADA System
               installed is intended to be permanently attached to earth and cannot be removed
               without causing substantial damage to the goods attached to earth. Furthermore,
               the parts are so interlinked to constitute a functioning SCADA System that none
               can be moved separately. The composite supply, therefore, amounts to erection
               and commissioning of an immovable property and classifiable as works contract
               as defined under Section 2(119) of the GST Act. In support of its argument the
               Applicant refers to the  Apex Court’s judgment  in  Solid and Correct Engineering
               Works [2010 (252) E.L.T. 481 (S.C.)], Virdi Brothers [2007 (207) E.L.T. 321 (S.C.)],
               TTG Industries Ltd. [2004 (167) E.L.T. 501 (S.C.)] and Triveni Engineering & Indus-
               tries Ltd. [2000 (120) E.L.T. 273 (S.C.)]. The Applicant also refers to a decision of
               the Appellate Authority for Advance Ruling, Rajasthan, in the case of RFE Solar
               Pvt. Ltd. [2019 (23) G.S.T.L. 378] and several rulings of the Authority for Advance
               Rulings at different States.
                       2.5  The Applicant submits that the works contract referred to above is
               ‘original work’ within the meaning of clause 2(zs)(ii) of Notification No. 12/2017-
               Central Tax (Rate), dated 28-6-2017, as amended. In support of its argument, the
               Applicant refers to the ruling of the Authority for Advance Rulings, New Delhi,
               in the matter of Hyundai Rotem Company [2016 (46) S.T.R. 801 (A.A.R.)] under the
               service tax regime.
                       2.6  The Applicant finally submits that the supply of the above compo-
               site supply of works contract as ‘original work’ to RVNL qualifies as a supply to
               railways and, therefore, eligible for GST under Entry 3(v)(a) of the Rate Notifica-
               tion.

                                    GST LAW TIMES      23rd April 2020      289
   164   165   166   167   168   169   170   171   172   173   174