Page 174 - GSTL_23rd April 2020_Vol 35_Part 4
P. 174

500                           GST LAW TIMES                      [ Vol. 35
                                     plant at Dabhol, Maharashtra and hereby engaged in the regasification of the
                                     LNG. Its GSTIN in the State of Maharashtra is 27AAGCK0390Q1Z0.
                                            2.  That, the LNG reaches to plant through jetty where it  is  unloaded
                                     from various ship/cargos. The captive jetty is situated in sea and it is about 1.8
                                     km from the tanks farm area and is well within the plant area. The length of the
                                     jetty is around 300 meters and handles presently around 20 LNG Cargo in a year
                                     without the breakwater.
                                            3.  That, in order to protect the jetty from the high tide and forceful sea
                                     waves, there is existing partly constructed break water which was constructed by
                                     Dabhol Power Company (DPC). This breakwater was the part of the original of
                                     the approved design  itself, meaning thereby, the jetty was not  workable  at its
                                     potential without the existence of breakwater.
                                            4.  That, the Breakwater was designed to prevent the high waves and
                                     tide to touch the jetty and cargo/ ships of LNG and thereby important for the
                                     safety for the jetty as well as the ship from the risk of damage.
                                            5.  That, although having the break water was  absolute necessity, the
                                     existing break water was not complete and requires immediate reconstruction in
                                     order to keep the jetty and cargo safe during the LNG unloading process.
                                            6.  That due to existing incomplete Break water facility, the NSPC, the
                                     authority for the clearance of jetty, provides only provisional clearances for the
                                     berthing and unloading of the LNG cargo and therefore does not allow the berth-
                                     ing of the cargo unless the height of the wave (swell) is less than 0.5 meters. Thus
                                     the performance of the jetty is much below its potential/capacity and that too has
                                     always suffers the risk of damage due to of high tides and waves.
                                            7.  That, due to the above mentioned operational technical restriction,
                                     the appellant has invited the tender where the scope of work are as follows -
                                            Basic design, detail engineering and physical model test, surveys, tempo-
                                            rary work, development of  quarries, supply of material, construction  of
                                            balance portion of breakwater and removal of temporary works as per the
                                            assessment reports, job specification, codes and recommendation of license
                                            holder and drawings.
                                            [*      *      *      *      *]
                                            8.  That for the purpose of determination whether the appellant will be
                                     able to claim the inputs on the GST paid on such construction/reconstruction of
                                     the break water, the appellant had preferred the application under section 97 of
                                     the GST Act and question for determination was as under -
                                            “Whether the appellant is eligible for taking ITC in terms of section 16 read
                                            with section 17 of the MGST Act/CGST Act (CGST/SGST/IGST) on con-
                                            struction of the above said Breakwater, which is an important and integral
                                            part of the existing jetty and very much required for the purpose of safety
                                            and longevity of the jetty and it imperative for making the existing jetty as
                                            fully workable as an all-weather jetty and hence improves the operational
                                            efficiency of the appellant.”
                                            9.  That the advance ruling authority on 24-5-2019 has passed the order
                                     under Section 98 and relying on Section 17(5)(d) read with explanation, held that
                                     the appellant is not allowed to take the credit of the ITC of the amount of the GST
                                     paid to the contractors/supplier of the goods or services. However, said order
                                     was communicated to us through Email dated 10-7-2019.

                                                          GST LAW TIMES      23rd April 2020      294
   169   170   171   172   173   174   175   176   177   178   179