158                           GST LAW TIMES                      [ Vol. 39
                                                  (d)  PMC has to review/help the procurement process and assist
                                                      the client in preparation of bidding documents, updating cost
                                                      estimates, bid invitation and bid evaluation, as required.
                                                  (e)  Provide training to PIU staff in project formulation, manage-
                                                      ment, monitoring and evaluation, financial, road safety and
                                                      environmental management aspects and community partici-
                                                      patory approaches of the project. The consultants has to con-
                                                      duct training at HQ office i.e. Vijayawada at a minimum of 2
                                                      trainings/years (or as advises by the client time to time). The
                                                      cost of training will be borne by the client.
                                                 Project management and monitoring
                                                  (a)  Planning, scheduling and monitoring of the project using MS
                                                      Project/PMIS/latest IT tools and techniques such  as online
                                                      monitoring of work sites with the aid of cyber tools, which
                                                      are under development.
                                                  (b)  Assist PMU/PIU/PRED in conducting regular meetings with
                                                      all stakeholders, contractors,  and other government entities
                                                      etc. to discuss progress and issues related to implementation,
                                                      and prepare minutes for recording and circulation.
                                                  (c)  Develop and implement procedures to support, monitor, re-
                                                      view  arid ensure the payment to contractors is well pro-
                                                      cessed, organized,  implemented and to ensure for timely
                                                      payment and monitor for compliance.
                                                  (d)  Ensure cost,  time and  quality compliance as envisaged  in
                                                      contract agreement, and
                                                  (e)  Identify  hindrances for implementation of contracts  and re-
                                                      solve the same with the help of respective agencies. Expertise
                                                      of PMC firm will be used by the PMU/PIU to make quick de-
                                                      cision so as to ensure timely completion of projects consistent
                                                      with quality within cost of estimates.
                                                 Review and revision of detailed project report
                                                  (a) Review/revise/modify & updating of existing detailed pro-
                                                      ject implementation reports with reference in following as-
                                                      pects.
                                                  (b)  Checking and field verification of existing DPRs including ef-
                                                      ficacy of DPRs and modification/revision of DPRs to achieve
                                                      required standards.
                                                  (c)  Review of each site environmental aspect for detailed design
                                                      of the project component.
                                                  (d)  Review of environmental safeguard  including impact as-
                                                      sessment, if any,
                                                  (e)  Review of Environmental Management Plan (EMP) and miti-
                                                      gation measures.
                                                 Construction supervision & contract management including OAC
                                                  (a)  Providing  advice  and guidance to  PMU/PIU (PRED) for
                                                      modern procedures  and guidelines for project  implementa-
                                                      tion and management in general.