2020 ]         IN RE : ZIGMA GLOBAL ENVIRON SOLUTIONS PVT. LTD.      185
                                 vided with proper gate to monitor incoming vehicles or other
                                 modes of transportation.
                            (d)  Contractor should provide weighbridge to  measure quantity
                                 of various  components of  waste  at  dumpsite is processed in
                                 terms of sorting and segregated materials, RDF, compost ma-
                                 terial, and inerts going out of the site.
                            (e)   The Contractor shall also provide fire protection measures and
                                 safety equipment.
                            (f)   The Contractor shall provide utilities such as drinking water
                                 facilities and  sanitary facilities (preferably  washing/bathing
                                 facilities for workers) and lighting arrangements for easy op-
                                 erations during night hours shall be provided and safety pro-
                                 visions including health inspections of workers at site shall be
                                 carried out.
                            (g)  In order to prevent environmental impacts of the activities the
                                 Contractor as per the SWM Rules, 2016 adopt guidelines for
                                 development of land fill as per Schedule-1 of the Rules.
                            (h)  Contractor shall set a soil and ground water baseline so that
                                 the same will be available to evaluate post Bio-mining and bi-
                                 oremediation/reclamation of the site.
                            (i)   Contractor shall monitor ground water quality, work zone air
                                 quality and ambient air quality  monitoring within the site
                                 from authorized laboratories/agencies and submit the report
                                 on monthly basis.
                            (j)   The Contractor shall monitor and measure noise levels at the
                                 site and interface of the facility with plant boundary and sur-
                                 rounding area.
                       (1.2.2)  Operation & Maintenance of Infrastructure and Equipment for 18
                       months
                       The Contractor shall be responsible for  construction, operation of site,
                       maintenance of transportation trucks,  mechanical lifting arrangements to
                       transfer the by-products into trucks, parking facilities, weighbridge, CCTV,
                       hook loaders, on Design Build Operate (DBO) basis. The Contractor should
                       maintain the facility and machinery in order to operate for the Contract pe-
                       riod.
                       (1.2.3)  Awareness & Extension Activities
                            (a)  The Contractor shall undertake a mass awareness/sensitiza-
                                 tion programme, in surrounding residential/village area, so as
                                 to ensuring the local people  are aware and taken into confi-
                                 dence of the bio-reclamation activities.
                            (b)  The Contractor shall create a sustained system of information,
                                 education and communication for  Bio-Mining & reclamation
                                 through collaborations with expert institutions and civil socie-
                                 ties and also disseminate through their own website.
                            (c)   The Contractor shall devise appropriate measures in consulta-
                                 tion with expert institutions for Bio-Mining & reclamation and
                                 for sale of recycle products in the best possible manner.
                            (d)  The Contractor can keep a track of the progress of its activities
                                 and establish  a database and update on a regular basis in-
                                 order to optimize its activities