Page 63 - GSTL_20th August 2020_Vol 39_Part 3
P. 63

2020 ]          IN RE : HALLIBURTON OFFSHORE SERVICES INC. (LIH)     277
                                 CONTRACTOR also to provide Drill water, Pot-water etc. for
                                 rigs, AHTSVs, PT/and other  OPERATOR’S vessels as  per
                                 Scope of Work. Vessels also have to carry HFHSD (free issue
                                 item by OPERATOR) for rigs from shore base.
                            (vii)  Subsea Well Heads, Running Tools including drill ahead tool
                                 and services including Service Engineer.
                            (viii) Liner Hanger Service along with crew.
                            (ix)  Miscellaneous Services like Coring (with Core Barrel & Core
                                 head), Casing & tubular running, Torque Turn (for premium
                                 casings & tubing up to 14” including tubing & landing string
                                 during completion), Hole  openers, Under-reamers,  Multiple
                                 Activation Circulating Bypass Tool (MACB), casing cutting &
                                 Fishing Tools, H2S equipment, 7” casing clean-out string and
                                 other tubular strings, odd size special drill bits, scrappers etc.
                            (x)  Capable and experienced services crew at Rig/Base personnel
                                 as per List of (Crew) Personnel and scope.
                            (xi)  It shall  be responsibility of  CONTRACTOR to provide  any
                                 cross-overs between its tools and drill stems of various rigs for
                                 which CONTRACTOR shall coordinate with Rig Contractors.
                            (xii)  It shall  be responsibility of  CONTRACTOR to provide  any
                                 items/equipment for making its units of various services/
                                 equipment compatible with  the rig power  supply for which
                                 CONTRACTOR shall interact with the Rig Contractor for
                                 timely mobilization and commencement of services.
                            (xiii) It shall be responsibility of  the CONTRACTOR to provide
                                 compatible units as per zonal requirements of Rig Safety like
                                 Zone 0, Zone 1 etc. and rig electrical supply.
                            (xiv) To take-up the job in accordance with the various articles and
                                 Schedule of Responsibilities.”
                       3.6  While performing the  aforesaid services,  at certain instances the
               equipment/tools  used by the Applicant for supplying oilfield services  get
               stuck/lost/damaged due  to uncontrollable or  unforeseen down  hole environ-
               mental situations in the oil and gas well and might not be retrievable. In such
               cases, the Querist receives reimbursement from the Customer towards such LIH
               equipment in terms of Clause 31 of the Contract entered by the Applicant with
               ONGC which reads as under :
                       “31.0  Loss or damage to CONTRACTOR'S down hole equipment
                       OPERATOR shall reimburse CONTRACTOR for loss of or damage to
                       CONTRACTORS down hole equipment, as under, provided that such loss
                       or damage is not occasioned by normal wear and tear or negligence on the
                       part of the CONTRACTOR or due to defective material.
                            (a)  In the case of  CONTRACTORS down hole equipment being
                                 damaged, Operator shall reimburse CONTRACTOR such re-
                                 pair cost, provided however, that OPERATOR shall not be re-
                                 quired to reimburse CONTRACTOR any amount greater than
                                 that which would have been  due had  such equipment been
                                 lost and, therefore, calculated under sub-section (b) hereinbe-
                                 low :-
                            (b)  In the case of CONTRACTOR’S down hole equipment being
                                 lost, OPERATOR will reimburse CONTRACTOR an amount
                                 limited to the  original cost (F.O.B. nearest  port) reduced  by
                                 depreciation at the rate of 10% per year to be proportioned for
                                 each completed month or part thereof from the date  of pur-
                                 chase of the lost equipment/tool subject to maximum depreci-
                                    GST LAW TIMES      20th August 2020      63
   58   59   60   61   62   63   64   65   66   67   68